February 2009

Sansuri Construction Progress Report : February 2009

The form work and the beams for the slab has been completed. A steel stair case has been erected to access the floor

The steel fixing is close to completion and the post tension company will come first week in March to install the post tension cables. The steel works will then be completed and we will prepare to pour the concrete to the slab